At the Nizhnyaya-Bureya hydroelectric power station accident
In the Amur region in the Nizhne-Bureiskaya hydroelectric power station accident occurred, according to the website of the station. Thursday, August 24, at 20:24 local time (14:24 GMT) during normal maneuvering in flight No. 1 of spillway dam there is damage to the shutter, which resulted in the flooding of the NPP platform. There were no injuries, the equipment of the turbine hall HPP received no damage. Currently, the water pass through HPP are carried out through one of the spans the spillway of the dam. Waste consumption at the level of 2600 cubic meters per second, the flow of about 700 cubic meters per second, the upstream water level 137,9 meters. Is drawdown the lower Bureya reservoir with the purpose of realization of repair work station area drained. As noted, such emissions do not pose a threat to settlements downstream. Flooding of settlements begins at discharges greater than 7500